Progress Energy / Intercession City Plant Hypalon Liner Repair
Project:
Project Contractor:
Polyurea Applicator:
System Applied:
Substrate / Area:
Date Completed:
Progress Energy / Intercession City Plant
F.S.I., Inc. of Fort Myers
F.S.I., Inc. of Fort Myers
Polyurea
26,000 sq. ft.
November 2003
Progress Energy was experiencing failure with their 5 year old Hyplon Liner. Liner was repaired many times without success.
After 8 months of observation of test area, Polyurea was selected for the project. With the capabilities of bonding and being able to address the damage.
The liner was washed down and primer applied to termination areas. 60-70 mils polyurea was applied with an additional 20 mils to seams and damaged areas. Project time with excavation was 6 days.